Monday, June 24, 2013

Basics of open cast blasting


  1.  Rock usually takes "60 ms(milli-second )" to move around "1 m".
  2. A blasting is said to healthy when it is free from fly rocks, with minimum vibration and boulders up to 1 %.
  3. Drilling and blasting cost should be within 22 % of the contract price.
  4. Minimum stemming of 3.5 meter should always be maintained.
  5. Efforts should be made to complete the blasting within 800 ms.
  6. Range of burden/spacing should be between 0.5 and 1.0.
  7. For optimum breakage, bench height/burden should be around 2.5.
  8. For satisfactory throw, bench height/burden should be greater than 2.5.
  9. Bench height should be between 10 and 12 m. 
  10. If the stemming height is 1.2 to 1.5 times the burden then fly-rock can easily be controlled.
  • bold parts are thumb rules.

Rock type(based on RMR)
Burden(in meter)(B)
Spacing(in meter)
Stemming(in meter)
Very poor
51 X D*
1.45 X B
1 X B
Poor
44 X D
1.34 X B
0.95 X B
Medium
37 X D
1.25 X B
0.95 X B
High
29 X D
1.19 X B
1.1 X B
Very high
23 X D
1.14 X B
1.1 X B

  • D: diameter of hole in mm (100,160,…..)

2 comments:

  1. Really a great blog with a best thoughts and ideas are shared thanks for sharing such an interesting article.
    Non Explosive Cracking Agent

    ReplyDelete
  2. Really a great blog with a best thoughts and ideas are shared thanks for sharing such an interesting article.
    Non Explosive Cracking Agent

    ReplyDelete

Reading is the 1st part of Commenting